Execution board

Tasks Board

A simple board view for non-technical teams to track ownership, due dates, and blocked work across projects.

Showing 20 of 20 tasks

Not started6

High

Issue owner turnover package

Harbor Point Multifamily Turnover

Sam RiveraAug 21, 2026 - Aug 31, 2026

Depends on: Close Level 12 punch list, Secure final elevator certification

Medium

Pilot standardized closeout checklist

Project Controls Standardization

Daniel BrooksAug 28, 2026 - Sep 12, 2026

Depends on: Train project managers on weekly controls

Medium

Launch 30-day warranty review

Harbor Point Multifamily Turnover

Noah KimSep 6, 2026 - Sep 14, 2026

Depends on: Issue owner turnover package

High

Publish commissioning and turnover plan

Riverside Medical Office Buildout

Sam RiveraAug 28, 2026 - Sep 27, 2026

Depends on: Release electrical switchgear for fabrication, Pass above-ceiling inspection in Phase 2

High

Baseline commissioning sequence

Northgate Distribution Center

Chris JonesSep 17, 2026 - Oct 22, 2026

Depends on: Publish six-week schedule recovery plan, Approve dock equipment change order

Medium

Launch monthly portfolio governance cadence

Project Controls Standardization

Lena OrtizSep 27, 2026 - Oct 27, 2026

Depends on: Validate portfolio cost dashboard

In progress6

Critical

Publish six-week schedule recovery plan

Northgate Distribution Center

Aisha RahmanAug 5, 2026 - Aug 17, 2026

Depends on: Resolve sprinkler redesign and hydraulic review

High

Close Level 12 punch list

Harbor Point Multifamily Turnover

Noah KimAug 11, 2026 - Aug 18, 2026

Depends on: Complete Level 12 owner quality walk

High

Train project managers on weekly controls

Project Controls Standardization

Sam RiveraAug 12, 2026 - Aug 20, 2026

Depends on: Approve standard RFI and submittal templates

Critical

Secure final elevator certification

Harbor Point Multifamily Turnover

Rita AlvarezJul 30, 2026 - Aug 22, 2026
Critical

Release electrical switchgear for fabrication

Riverside Medical Office Buildout

Daniel BrooksJul 24, 2026 - Aug 25, 2026

Depends on: Complete MEP coordination clash review

High

Validate portfolio cost dashboard

Project Controls Standardization

Lena OrtizAug 8, 2026 - Aug 27, 2026

Blocked3

Critical

Resolve sprinkler redesign and hydraulic review

Northgate Distribution Center

Maya ChenJul 20, 2026 - Aug 7, 2026
Critical

Pass above-ceiling inspection in Phase 2

Riverside Medical Office Buildout

Chris JonesAug 1, 2026 - Aug 11, 2026
Critical

Approve dock equipment change order

Northgate Distribution Center

Lena OrtizAug 3, 2026 - Aug 14, 2026

Done5

High

Close permit coordination package

Riverside Medical Office Buildout

Chris JonesMay 13, 2026 - Jun 12, 2026
Medium

Approve standard RFI and submittal templates

Project Controls Standardization

Sam RiveraJul 20, 2026 - Aug 4, 2026
Critical

Complete structural steel topping out

Northgate Distribution Center

Aisha RahmanJun 19, 2026 - Aug 7, 2026
Critical

Complete MEP coordination clash review

Riverside Medical Office Buildout

Maya ChenJul 16, 2026 - Aug 10, 2026

Depends on: Close permit coordination package

High

Complete Level 12 owner quality walk

Harbor Point Multifamily Turnover

Daniel BrooksAug 4, 2026 - Aug 10, 2026